Sketches

Tuesday 27 March 2012

TA Cap

On Chemelot (the chemical plant where I work presently) massive renovation works take place, called TA/CAP . They do that every 10 to 15 years.
An extra of 1200 workers are brought in, continuously dismantling installations and building new ones. As the works have to be done in something like 8 weeks, works go on 24/7.
Here a sketch of one of the numerous mammoth cranes on the terrain.
Renovatie werken aan een van de productielijnen op het Chemelot terrein, Geleen.

2 comments:

schilderijenfoto said...

Heerlijke schets. Ik zie veel overeenkomst met mijn bomen ;-)

Rene Fijten said...

Bedankt Geert-Jan. Metalen bomen...